Corporate Issuers. Worth 6 to 9 percent of the exam. One session: the lesson, the rules, the method, then the questions.
The full lesson page · Back to your cockpit
Five to ten minutes on this one unit: what the exam wants, the idea in plain words, then straight into the trap and the practice.
The exam wants you to calculate net present value and internal rate of return, decide which one governs when the two methods disagree, describe why IRR's reinvestment assumption is less realistic than NPV's, and identify which cash flows belong in the analysis in the first place, excluding sunk costs and including opportunity costs.
Net present value discounts every cash flow a project produces at the firm's required rate of return, sums those present values, and nets out the initial cost. A positive NPV means the project is expected to return more than its cost of capital, and that surplus, expressed in today's dollars, is exactly how much value the project adds to the firm. Accept when NPV is positive; that single rule is the whole decision.
Internal rate of return asks a related but different question: at what discount rate does this project's NPV fall to exactly zero. For an independent project with a conventional cash flow pattern, one initial outflow followed only by inflows, NPV and IRR always agree on accept or reject. They can disagree sharply once two projects are compared against each other, because IRR is a rate and NPV is a dollar amount, and a smaller project can carry a higher rate while creating less total wealth. When mutually exclusive projects conflict, only one of which can be undertaken, NPV governs the choice every time, regardless of how the two IRRs compare. A project creating $200,000 of value at 14 percent is worth more to owners than one creating $100,000 at 18 percent, because NPV measures wealth and IRR only measures a rate.
The disagreement traces back to a hidden assumption each method makes about reinvestment. IRR implicitly assumes every interim cash flow can be reinvested at the IRR itself, an assumption that grows less realistic the higher that IRR climbs. NPV assumes reinvestment at the firm's own required return, the more defensible assumption, which is exactly why NPV is the theoretically preferred method for ranking competing projects.
Only cash flows the decision actually changes belong in the analysis. A sunk cost, money already spent regardless of what is decided now, never enters the calculation, because no choice available today can recover it or change it. An opportunity cost, the value given up by using an asset the firm already owns for this project instead of its next best use, must be included even though no new cash physically changes hands. Financing costs, interest and dividends among them, stay out of the cash flow stream entirely, because they are already captured inside the discount rate itself; including them there and again in the cash flows double-counts the cost of financing.
When a firm cannot fund every positive-NPV project because its capital budget is limited, the profitability index, the present value of future cash flows divided by the initial investment, ranks independent projects to maximize total value created within that constraint. Raw NPV cannot do this job on its own, since it favors larger projects regardless of how efficiently they use scarce capital. The profitability index has no role, however, in ranking mutually exclusive projects of different sizes; NPV still governs that decision, exactly as it does when no capital constraint exists at all.
A project costs $250,000 today and is expected to generate $80,000 per year for 4 years. The firm's required return is 9 percent. What is the project's NPV, and should the firm accept it? PV of the annuity = $80,000 x [1 - (1.09)^-4] / 0.09 = $80,000 x 3.2397 = $259,177.59. NPV = $259,177.59 - $250,000 = $9,177.59. Because NPV is positive, the firm should accept the project: it is expected to return more than the 9 percent required return and adds about $9,178 of value.
Same project: $250,000 initial cost, $80,000 per year for 4 years, required return 9 percent. Set up the present value of the annuity yourself, then net out the initial cost to find NPV.
Initial cost $250,000. Cash inflow $80,000/year for 4 years. Required return 9%. Find NPV.
A higher IRR only means a higher rate, never automatically more value; whenever two mutually exclusive projects disagree on NPV and IRR, NPV wins the decision every time, because it measures wealth in dollars and IRR does not.
Read these before the questions, not after them. Everything here traces to this module's own lesson and to the 2026 outline.
Net present value equals the sum of each period's cash flow discounted at the firm's required rate of return, netted against the initial outlay; a positive NPV means the project is expected to return more than its cost of capital and adds that amount of value to the firm. For independent projects with conventional cash flow patterns, the NPV and IRR accept-or-reject decisions agree; they can disagree only when projects are compared against each other for a single choice, or when cash flows are non-conventional.
Internal rate of return is the discount rate that sets a project's NPV to zero, and it implicitly assumes every interim cash flow can be reinvested at that same rate, an assumption that grows less realistic as the IRR itself grows large. NPV's reinvestment assumption, the firm's own required return, is the more defensible one, which is why NPV, not IRR, is the theoretically preferred ranking method whenever the two disagree.
When only one of two or more competing projects can be undertaken, ranking by IRR can select the project that creates less total value, because IRR is a rate and NPV is a dollar amount; the CFA curriculum's position is unambiguous that NPV governs the ranking decision whenever mutually exclusive projects are involved, regardless of how the IRRs compare.
Return on invested capital compares a company's after-tax operating profit to the capital invested to generate it, evaluating how efficiently capital already committed is being used, rather than whether a specific future project should be undertaken. NPV and IRR are forward-looking project-selection tools; ROIC is a backward-looking measure of how well past capital allocation decisions are performing, and the two families of measures answer different questions even though both are part of the capital allocation toolkit.
A sunk cost, money already spent regardless of the decision at hand, never belongs in a capital budgeting cash flow, because it cannot be changed by the decision being made now. An opportunity cost, the value given up by using an asset the firm already owns for this project instead of its next-best alternative use, must be included even though no new cash changes hands. Financing costs, such as interest expense, are captured in the discount rate itself and must not also be subtracted from the cash flows, which would double-count the cost of debt.
When a firm cannot fund every positive-NPV project because its capital budget is limited, ranking independent projects by profitability index, the present value of future cash flows divided by the initial investment, maximizes total value created within that constraint, something raw NPV cannot do on its own because it favors larger projects regardless of capital efficiency. Profitability index still fails as a ranking tool for mutually exclusive projects of different scale, where NPV remains the correct criterion.
A project creating $200,000 of value at 14% is worth more to owners than one creating $100,000 at 18%. When NPV and IRR disagree on a mutually exclusive choice, the dollar figure wins every time.
Money already spent does not belong in the decision no matter how large it was or how tempting it feels to justify past spending. Continuing a project purely because of what has already been spent on it is the sunk cost trap in its purest form.
Profitability index ranks independent projects competing for a limited budget. It does not fix the scale problem when two mutually exclusive projects of different sizes are compared; NPV still governs that decision.
The order to work a question of this type in, every time, before you touch the numbers.
The first is worked in full. The second gives you the setup and stops. After that the questions give you nothing, which is the point: the help fades on purpose, so the last thing you practise is the thing the exam actually asks of you.
An analyst is evaluating two mutually exclusive projects. Project Alpha has an NPV of $120,000 and an IRR of 14%. Project Beta has an NPV of $95,000 and an IRR of 18%. The firm's required rate of return is 10%. Which project should the firm select, and which method should most likely guide the decision?
Answer A. The correct answer is Project Alpha. NPV is the preferred method for mutually exclusive projects because it directly measures value added to the firm. Project Beta's higher IRR does not mean it adds more wealth. It means it earns a higher percentage return on a potentially smaller or differently-timed cash flow base. NPV of $120,000 exceeds NPV of $95,000, so Alpha creates more shareholder value..
A project has the following cash flows: Year 0: -$50,000; Year 1: $30,000; Year 2: $20,000; Year 3: $15,000. The firm's WACC is 12%. What is the project's NPV (nearest dollar), and should it be accepted, most likely?
Identify whether the projects under comparison are independent (evaluate each on its own NPV or IRR against the hurdle rate) or mutually exclusive (rank by NPV only).
Answer A. The correct answer is NPV = -50,000 + 30,000/1.12 + 20,000/1.12^2 + 15,000/1.12^3 = -50,000 + 26,786 + 15,944 + 10,677 = $3,407. Since NPV > 0, accept the project. On BA II Plus: CF0=-50000, C01=30000, C02=20000, C03=15000, I=12, NPV=CPT..
Pick an answer, say how sure you are, then reveal. Being sure and wrong is the most useful thing that can happen in a session, so answer honestly: it sends the unit back to learning and puts it at the front of your revision queue.
The IRR of a project is 15%. The firm's WACC is 12%. A key assumption embedded in the IRR calculation is that interim cash flows are most likely reinvested at:
How sure are you?
Unit: capital-investments-and-capital-allocation
A project costs $100,000 today. It generates cash inflows of -$30,000 in Year 1, +$200,000 in Year 2, and -$50,000 in Year 3. How many IRRs might this project most likely have?
How sure are you?
Unit: capital-investments-and-capital-allocation
A project has an initial cost of $80,000 and generates annual cash inflows of $25,000 for 5 years. What is most likely the payback period?
How sure are you?
Unit: capital-investments-and-capital-allocation
Which of the following is LEAST likely a limitation of the payback period method?
How sure are you?
Unit: capital-investments-and-capital-allocation
Project X has an initial investment of $500,000 and an NPV of $60,000. Project Y has an initial investment of $100,000 and an NPV of $30,000. The projects are mutually exclusive. Using the profitability index, which project ranks higher. And does the CFA curriculum support this ranking, most likely?
How sure are you?
Unit: capital-investments-and-capital-allocation
When evaluating a proposed plant expansion, which of the following costs should most likely be included in the project's incremental cash flows?
How sure are you?
Unit: capital-investments-and-capital-allocation
Two projects have equal NPVs at the firm's WACC of 9%. Project A generates large cash flows early; Project B generates large cash flows late. At which discount rate would most likely Project B's NPV be higher than Project A's?
How sure are you?
Unit: capital-investments-and-capital-allocation
According to the CFA curriculum, which capital budgeting method is MOST appropriate when a firm faces capital rationing and must choose among several independent projects?
How sure are you?
Unit: capital-investments-and-capital-allocation
A company evaluates a project with an initial cost of $1,000,000, WACC of 10%, and cash inflows of $300,000, $400,000, and $600,000 in years 1 through 3. Combining the NPV and IRR decision rules, an analyst who finds IRR is approximately 19% but incorrectly concludes the project should be rejected because '19% seems low compared to some of the firm's other opportunities earning 25%' has most likely made an error because:
How sure are you?
Unit: capital-investments-and-capital-allocation
A firm has two mutually exclusive projects of different scale: Project Small costs $100,000 with an IRR of 40%, and Project Large costs $1,000,000 with an IRR of 18%, both using the firm's 10% WACC. Project Small's NPV is $15,000; Project Large's NPV is $120,000. Combining the NPV and IRR decision rules for mutually exclusive projects, the firm should most likely:
How sure are you?
Unit: capital-investments-and-capital-allocation